Phase B
(COMPLETED)
September 2017
Phase B of our capital project is in its final stretch. Below, is a building-by-building summary of work currently taking place or that has recently been completed.High School
Current
• Courtyard construction• Sidewalk replacement
• Kitchen/cafeteria renovations
• Bathroom renovations near cafeteria
• New doors and window façade at gym and auditorium entrances
• New floors in select areas
• New electronic school sign at front entrance
• IT upgrades
Completed
• New flag pole installed• New lighting/ceilings in select areas
• New student lockers
• HVAC upgrades
Middle School:
Current
• New student lockers• Bathroom renovations
• Auditorium lighting upgrades
• Elevator upgrades
• New electronic school sign at front entrance
Completed
• Sidewalk replacement (75% complete)• New granite curbing and drainage installed
• New exterior doors in select areas, including auditorium
• New drinking fountains
• Structural steel installed in gym for new HVAC rooftop units
Deerfield Elementary School:
Current
• Hallway painting• New floors in hallways and faculty room
• Carpet installation in library
Completed
• Bathroom renovations• New lighting/ceilings in select areas
Hart’s Hill Elementary School:
Current
• Bathroom renovations in Room 2• New lighting/ceilings in select areas
Completed
• Bathroom renovationsMarcy Elementary School:
Current
• Renovations on connecting corridor between main and kindergarten buildings• Main entryway sidewalk replacement
• Bathroom renovations
Westmoreland Road Elementary School:
Current
• Drainage and blacktop replacement in back of school• Carpet replacement in library and computer lab
• New tile floors in abated areas
Completed
• Bathroom renovations• Hallway painting
• New lighting/ceilings in select areas
Chiz Frye Field Press Box:
Current
• Sheetrock and room partitions, site work, lighting and door installation, painting, IT workCompleted
• Roof, siding, elevator installedAll current/ongoing work is expected to be completed by the first day of school except:
• Courtyard construction (High School)• Bathroom renovations in Room 2 (Hart’s Hill)
• Lighting upgrades (Middle School)
In an effort to eliminate and/or minimize disruptions during the school day, most of the remaining work will take place after school hours. The long-term results of our capital project will enhance the learning environment for our students, improve building safety and address various infrastructure-related needs. Thank you for your continued patience and support. To view photos of ongoing and completed work, visit www.wboro.org/capitalproject.
July 2017
The work associated with Phase B of our Capital Project continues to progress.Completed Work (since the last update):
Bathroom renovations at Deerfield Elementary, Hart’s Hill Elementary and Westmoreland Road ElementaryBuilding-by-building summary of work currently taking place:
Deerfield Elementary – hallway flooring replacement; hallway painting; library carpeting replacement; miscellaneous floor abatement; new handicap lift
Hart’s Hill Elementary – hallway ceiling removal and replacement; miscellaneous asbestos abatement; new kindergarten bathroom
Marcy Elementary – final bathroom renovations; renovations on connecting corridor between main and kindergarten buildings
Westmoreland Road Elementary – library/media center carpeting replacement scheduled to begin; hallway painting scheduled; miscellaneous floor abatement; new handicap lift
Middle School – bathroom renovations to be completed this summer; student locker replacements scheduled to begin; elevator upgrades; new handicap lift
High School – bathroom renovations to be completed this summer; miscellaneous HVAC work; courtyard and kitchen renovations
Transportation Garage – exterior siding to be installed on offices; site work improvements scheduled to begin
Press Box at Chiz Frye – siding being installed; interior nearing completion; site improvements to begin when press box is nearly complete
The long-term results of our capital project will enhance the learning environment for our students, improve building safety and address various infrastructure-related needs.
Thank you for your continued patience and support.
May 2017
The work associated with Phase B of our Capital Project continues to progress. In an effort to eliminate and/or minimize disruptions during the school day, the vast majority of work is taking place after school hours, except the construction of the new Chiz Frye Field Press Box and the renovations at the Transportation Garage. The following is the latest update.Completed Work:
• Transportation garage lifts• Transportation garage office interior
• New ceilings and lighting in multiple school buildings
• New classroom doors at Westmoreland Road Elementary
• Several bathrooms in multiple school buildings are back in service
Building-by-building summary of work currently taking place:
Deerfield Elementary – bathroom renovations on-going; hallway flooring replacement; hallway paintingHart’s Hill Elementary – bathroom renovations nearing completion; hallway ceiling removal and replacement beginning
Marcy Elementary – bathroom renovations nearing completion; renovations on connecting corridor between main and kindergarten buildings beginning
Westmoreland Road Elementary – bathroom renovations on-going; library carpeting replacement scheduled to begin at the end of the school year; hallway painting scheduled
Middle School – bathroom renovations on-going; student locker replacements scheduled to begin at the end of the school year
High School – bathroom renovations on-going; student locker replacements on-going; HVAC work, courtyard and kitchen renovations scheduled to begin at the end of the school year
Transportation Garage – exterior siding to be installed on offices; bus wash nearing completion; site work improvements scheduled to begin at the end of the school year
Press Box at Chiz Frye – masonry work, metal framing work and electrical work on-going; site improvements scheduled to begin when press box is nearly complete
The long-term results of our capital project will enhance the learning environment for our students, improve building safety and address various infrastructure-related needs.
We ask for your continued patience and support.
February 2017
The work associated with Phase B of our capital project continues to progress.In an effort to eliminate and/or minimize disruptions during the school day, the vast majority of work is taking place after school hours, except the construction of the new Chiz Frye Field Press Box and the renovations at the Transportation Garage.
The new press box is moving along nicely, and the steel components will soon be erected. The interior work at the Transportation Garage is nearing completion. The new bus wash is also nearing completion, and the new bus lifts are already in use.
Below is a building-by-building summary of additional work currently taking place:
Deerfield Elementary School – bathroom renovations, ceiling replacements, electrical workHart’s Hill Elementary School – bathroom renovations, ceiling work scheduled to begin
Marcy Elementary School – bathroom renovations
Westmoreland Road Elementary School – bathroom renovations, ceiling replacements, electrical work
Middle School – bathroom renovations
High School – bathroom renovations, ceiling replacements, electrical work, HVAC work, student locker replacement
District-wide – technology upgrades
All in-progress bathroom renovations are scheduled to be completed by early March. Once completed, additional bathroom renovations will start.
The long-term results of our capital project will enhance the learning atmosphere for our students, improve building safety and address various infrastructure-related needs.
We ask for your continued patience and support.